Findings of the National Fact-Finding Mission on the House Technology Industries Factory Fire

February 14, 2017

I. Introduction

Background

On February 1, 2017, at around 6 PM, a fire broke inside the premises of the three-storey building owned by HTI. Accounts from the workers indicated that between 1,000-2,000 workers were inside the building at that time. Some of the workers were about to leave HTI and some were coming in for their shift.

Authorities declared the fire under control on February 2 at 12:30 PM. However, the building continued to emit heavy smoke flames again by 7 PM until about past 11 PM. By February 3, BFP Region IV-A Director Sergio Soriano officially declared “fire out.” On February 4, the Governor of Cavite said that there were no fatalities, only the 126 workers injured and that all employees have been accounted for.

On February 2, CTUHR, IOHSAD, EILER and KMU dispatched a Quick Response Team and initial fact-finding Mission in the area to check on the situation. Cavite-based organizations also joined and kept a round-the clock incident monitoring until the morning of February 4. Interviews with HTI workers in surrounding communities were conducted, and all of the respondents remarked that many were trapped and presumed dead inside the burning building, contrary to the prior announcement of Cavite Governor Boying Remulla.

Workers’ and witnesses claims prompted a much broader NFFM on February 4 and 5.

Read the full report here